MSE Engenharia shares updates about the project at the Itaipu construction site in Foz do Iguaçu, Paraná. Committed to high quality standards, our team has been working to achieve our objectives.

We have already completed more than 68.35% of the work, which is a solid indication of our commitment to strictly complying with delivery times and maintaining a consistent quality standard.

Civil construction is progressing rapidly, with the completion of 91% of the work. This advance evidences the firm progress we are making in construction, establishing a solid foundation for the overall structure.

As electrical installations are already 44% completed, demonstrating our commitment to ensuring an efficient and reliable energy supply, essential for a project of this magnitude.

Connectivity is critical, and we're making great progress, with 78% of telecom installations already completed, ensuring that communication is effective at every stage of the project.

Safety is an undisputed priority, and we have good news in that regard. 73% of fire fighting and prevention facilities have already been completed, ensuring a safe environment for everyone involved.

When it comes to comfort and efficiency, we're making good headway, with 57% of air conditioning installations already completed to create a pleasant environment in all areas of the project.

And finally, 92% of hydraulic and hydrosanitary installations are already completed, ensuring an efficient and reliable use of water resources.

These numbers reflect MSE Engenharia's commitment to the Itaipu project. We're looking forward to sharing more updates as we move forward. We thank everyone involved for their dedicated work.