Data Center Installations

Data Center
MSE Engenharia is a data center engineering and installation company with 47 years of experience in Brazil. We deliver MV/LV electrical, fire protection, automation and L1–L5 commissioning for data centers, from construction to first power, with our own team and switchgear factory.
In short

MSE Engenharia is a Brazilian data center engineering and installation company with 47 years of experience. It delivers medium- and low-voltage electrical installations, fire protection, automation/BMS and L1–L5 commissioning for colocation and hyperscale data centers across Brazil. Delivered jobs include a +9 MVA data center with 6 MW of IT load and 240 km of conductors, the 1,828 m² Itaipu Binacional data center and installations for the general contractors of global operators in São Paulo. It serves operators, general contractors and integrators, from mobilization to assisted start-up.

Updated September 2026.
Data center installations.
In a data center, every delayed circuit is a hall standing still, and every installation failure becomes an uptime risk. The client needs redundant power, fire protection and automation working from day one.
‍
For 47 years we have been delivering installations for operations that cannot stop. Electrical, fire protection, automation and systems executed by our own team, with factory-built e-houses and full commissioning before energization.
Complete Installations
Medium and low voltage, generators, UPS, fire protection, automation and cabling executed by the same team. Fewer interfaces, less rework, more uptime.
Data Center Experience
Work delivered for colocation, hyperscale and the power sector. Over 240 km of conductors pulled on a single job.
In-House Team and Factory
Our own electricians, fitters and technicians in the field. E-houses and switchboards leave our factory tested and arrive ready to connect.

Data Center - Hortolândia SP

Installations for Construtora Racional - Microsoft
+ 12 MVA of electrical power
+ 200 km of low-voltage electrical conductors
+ 20 km of electrical and systems infrastructure
+ 1 km of aluminum busway
4 medium/low-voltage transformers of 2.5 MVA
+ 4 generator sets of 3,000 kVA and UPS
+ 60 low-voltage switchboards

Data Center - Jundiaí and Paulínia SP

Installations for Construtora Construcap - AWS
+ Phases 1 to 6
+ Medium and low voltage: switchboards, transformers and busway
+ Generator sets, UPS and electrical infrastructure
+ Coordination and selectivity study
+ Commissioning: arc flash, TCC curves and current injection tests
+ Firestop

Itaipu Binacional
Data Center

Foz do Iguaçu - PR - Tier III
+ 1,828 m² of built area
+ 40.2 km of low-voltage electrical cables
+ 238 m³ of deep foundations and caissons
+ 168 m of cast-in-place piles
+ 92 tons of steel structure

Tecto Data Center

Santana de Parnaíba - SP - Construction management
+ Protected CAPEX

Scala Data Center

One of the largest data centers in operation in Brazil: +9 MVA, 6 MW of IT load and 240 km of conductors executed by MSE.

Barueri - SP - TB12 and TB00
+ 9 MVA of electrical power
+ 6 MW of IT capacity
+ 240 km of low-voltage electrical conductors
+ 20 km of electrical and systems infrastructure
+ 1.5 km of medium-voltage electrical conductors
+ 5.3 km of fire protection piping
+ 200 m of 4,000 A aluminum busway
5 medium/low-voltage transformers of 3,300 kVA
+ 117 low-voltage switchboards
7 medium-voltage switchboards
5 generator sets of 3,000 kVA and UPS systems
8 pre-action valves
Firestop
Serviços

Instalações que sustentam o uptime

Installations

Electrical, fire protection, automation and systems under a single point of responsibility. From the utility connection point to the rack, with our own team and integrated commissioning.

Substation, Medium and Low Voltage

HV/MV substation, transformers, MV and LV switchboards, busway and conductors all the way to the data halls. Power distributed with circuit-by-circuit traceability.

Generators, UPS and Diesel

Generator sets, double-conversion UPS, batteries and diesel storage and distribution. N+1 and 2N topologies, with no single point of failure.

E-Houses and Electrical Switchboards

E-houses, switchboards, PDUs and STSs built and tested in our own factory. They arrive on site ready to connect, shortening the path to first power.

Fire Protection

Sprinklers with pre-action valves, hydrants, pumps, piping networks and firestop sealing. Protection against accidental discharge inside the data halls.

Detection and Gas Suppression

Early aspirating smoke detection, fire alarm systems and clean-agent suppression. Fire is identified and contained before it reaches the IT equipment.

Automation and Monitoring

Integrated PLC, BMS and EPMS, with relay parameterization and real-time supervision of power and alarms.

Electronic Security and Cabling

CCTV, access control, perimeter alarm and structured cabling in accordance with TIA-942 and TIA-568.

Infrastructure and Cable Trays

Cable trays, ladder racks, channels, baskets and conduit runs sized for the data halls. Routes separated by voltage and system, ready for expansion without rework.

Civil Structure and Raised Floor

Slab reinforcement for racks, UPS systems and batteries. Raised floor with a service void for air and cables, or a solid slab with overhead distribution.

Tier III Certification

Experience in Tier III data centers, with concurrent maintainability and redundant paths. Documentation, tests and as-built prepared for Uptime Institute certification.

L1–L5 Commissioning

Current injection, arc flash, selectivity and integrated tests from level 1 to 5. Redundancy proven before first power. References: ASHRAE Guideline 0, Uptime Institute, NFPA 70E.

Get in touch
with our engineering team.

Our approach to quality and commissioning delivers data centers ready to operate 24 hours a day, 7 days a week, 365 days a year.

At MSE Engenharia, we understand that speed of deployment, reliability and predictability are essential in data center construction. That is why we work in an integrated way, from construction planning through building, assembly, testing and commissioning.

Data Center Tier III Itaipu - MSE Engenharia
Data Center TB12 Scala Barueri - MSE Engenharia
Instalações elétricas data center Hortolândia - MSE Engenharia
Data Center Tier III Itaipu - MSE Engenharia
Painéis elétricos Scala Tepozpark México - STI Electric
Data Center TB12 Scala Barueri - MSE Engenharia

The 15 steps of a data center installation

The sequence of a data center build, from the initial study to first power. Each step is detailed in the full guide.

1
Conceptual study: MW, rack density and electrical topology
2
Basic and detailed engineering (IFC)
3
Procurement of long-lead items: transformers, generators and UPS
4
Earthworks, foundations and structure
5
Electrical rooms and HV/MV substation
6
E-houses, switchboards and busway
7
Generator sets, UPS and diesel system
8
Infrastructure: cable trays, ladders and pipe racks
9
MV/LV power cabling to the data halls
10
Structured cabling and electronic security
11
Fire protection: pre-action, detection and gas suppression
12
Automation: PLC, BMS and EPMS
13
Commissioning L1–L3: inspections, factory and field tests
14
Commissioning L4–L5: integrated tests under load and redundancy
15
First power, as-built and assisted operation
Read the full 15-step guide →

How data center construction works

Building a data center is not a civil works job with equipment inside. It is a build in which power and network define the schedule, and in which any mismatch between engineering and execution becomes an availability risk. That is why choosing a data center construction company with its own team changes the outcome.

The stages of a data center build

A data center goes through three phases: engineering (conceptual, basic and detailed), construction and installations (civil, electrical, fire protection and automation) and commissioning through first power. The work begins with the conceptual study, which defines capacity in MW, rack density and electrical topology. Then come basic engineering, detailed engineering and the issue of construction documents. Only then do earthworks, foundations, structure, electrical rooms, substation, diesel system and network come in.

How long it takes to build a data center

Building a mid-sized data center takes 12 to 24 months, from the initial study to energization. What delays the work most is not the civil works: it is the long-lead equipment, such as transformers, generators and UPS, which can take 8 to 14 months to arrive. Specifying these items during the engineering phase is what protects the schedule.

How much it costs to build a data center

The cost of a data center is driven by installed electrical power (MW) and by the level of redundancy, not by built area. A 5,000 m² hall with 2 MW and a 5,000 m² hall with 10 MW are completely different jobs. The power infrastructure available at the site and the required Tier level also weigh heavily.

Tier 2, Tier 3 and Tier 4: what changes on site

Tier 2 has redundant components, Tier 3 allows any component to be maintained without shutting down the load, and Tier 4 tolerates faults with independent systems. The classification, also written as Tier II, Tier III and Tier IV, is defined by the Uptime Institute. A Tier 3 data center requires redundant power paths; in Brazil, it is the most requested level for colocation data centers. The higher the level, the greater the impact on layout, substation and cost.

EPC turnkey or separate contracts

In the EPC turnkey model, engineering, construction, assembly and commissioning stay under a single point of responsibility; in separate contracts, each discipline answers only for its own part. Hiring engineering, the builder and the installer separately looks cheaper on paper, but it creates gray areas between contracts, and that is where rework and delays appear. In data centers, turnkey reduces interfaces exactly where availability risk is highest.

We develop solutions for data centers,
from construction to commissioning,
with first power on schedule.

Frequently asked questions

What does the electrical installation of a data center include?

HV/MV substation, transformers, medium- and low-voltage switchboards, busway, generators, UPS and distribution down to the racks — with circuit-by-circuit traceability and commissioning before first power.

Do you also execute fire protection, in addition to electrical?

Yes. Pre-action sprinklers, hydrants, aspirating smoke detection and clean-agent suppression, all by the same in-house team.

What is L1–L5 commissioning and why does it matter?

They are five levels of testing, from factory inspection to integrated tests under load. Each system is validated before energization, proving N+1 or 2N redundancy.

Do you manufacture the switchboards and e-houses yourselves?

Yes. They leave our own factory tested and arrive on site ready to connect, reducing interfaces and shortening the path to first power.

Can you install in a data center that is already in operation?

Yes. Hall expansions and system upgrades are carried out with a work plan that preserves the availability of the existing operation.

Vocês atendem data centers em todo o Brasil?

Sim. A MSE executa instalações para data centers em todo o território nacional, com equipes próprias mobilizadas por obra. Painéis elétricos da fábrica do grupo também já foram fornecidos para data center no México.

Terms used in this project

Tier III data center

Tier III is the Uptime Institute classification for concurrently maintainable data centers: any component can be maintained without shutting down the IT load, which requires redundant power paths.

L1–L5 commissioning

A five-level testing process, from factory inspection (L1) to integrated tests under load with failure simulation (L5), that proves redundancy before first power.

BMS and EPMS

BMS is the building management system that supervises utilities and alarms; EPMS is the electrical power management system that monitors substation, generators, UPS and switchboards in real time.

Colocation and hyperscale

Colocation is a data center that leases space and power to multiple customers; hyperscale is a large data center built for a single cloud operator, usually above tens of MW.